Fort Boone Pump Station Replacement
FRANKLIN COUNTY, KY
WATER RESOURCES
The Fort Boone Pump Station Relocation and Capacity Upgrade project demonstrates Palmer Engineering’s expertise in water and wastewater infrastructure design, strategic planning, and stakeholder coordination.
The existing Fort Boone Pump Station was an aging facility and a recurring source of Sanitary Sewer Overflows (SSOs). To resolve these issues, Palmer Engineering designed a new, larger-capacity pump station downstream, allowing for the future elimination of three private pump stations while accommodating additional flows and inflow/infiltration.
The Fort Boone Pump Station Relocation Project is a prime example of Palmer Engineering’s ability to deliver cost-effective wastewater infrastructure solutions while improving system reliability, reducing overflows, and collaborating with key stakeholders.
Unique aspects
-
Opportunities
Data-driven planning: PER evaluated three alternatives considering sewershed impacts, capital and O&M costs, and overall collection system capacity.
Future flexibility: Recommended solution maintained adaptability for long-term system needs and I/I management.
Strategic partnership: Coordination with Buffalo Trace Distillery enabled decommissioning of two private pump stations and transfer of the shared force main to FSD.
Streamlined delivery: Early engagement with multiple property owners created a clear path for easement acquisition and schedule certainty.
-
Challenges
Unmapped utility conflict: Discovery of a gas line required intensive utility coordination and design revisions to resolve safely.
Contractor turnover: Initial contractor abandoned the site; design had to be adapted to account for partially completed work and to re-mobilize with a new contractor.
Multi-stakeholder logistics: Aligning needs of FSD, private owners, and utility providers while maintaining momentum and budget.
-
Successes
Optimized solution identified: PER process selected the most cost-effective alternative while improving capacity and collection system performance.
Capital & lifecycle savings: Decommissioning two private stations and FSD’s ownership of the force main reduced construction costs and long-term O&M expenses.
Resilient project management: Rapid redesign and coordination kept the project on track despite unexpected field conditions and contractor changes.
Efficient investment: Delivered scope—pump station relocation, capacity upgrades, easements, stakeholder coordination, and system integration—within a budget framework of $500,000 (estimated construction) and $60,700 (engineering fees).
Key Team Members
-

Brian Ward, PE, PLS
TEAM MEMBER
-

Stephanie Blain, PE, LEED AP
TEAM MEMBER